6. Consider Field Joint Coating
One point is often overlooked during procurement: factory-applied 3PE coating does not cover the areas exposed during field welding. After pipes are joined, the bare steel around the girth weld needs a suitable field joint coating system. ISO 21809-3 specifically addresses the qualification, application, and testing of field joint coatings for buried and submerged pipeline systems. Therefore, buyers should confirm that the factory coating, pipe-end cutback, and field joint coating method are compatible. Factory coating + field joint coating = complete external corrosion protection
7. Consider Transportation and Handling
A properly manufactured coating can still be damaged during loading, transportation, storage, or installation. The purchase specification should therefore address:
-
Pipe stacking
-
Lifting method
-
Protective materials
-
Contact points
-
End protection
-
Marking
-
Packaging requirements
For export projects, transportation conditions should be considered before shipment, especially when pipes will experience long-distance road, rail, or marine transportation.
8. Compare Total Project Value, Not Only Price
The lowest coating price does not necessarily produce the lowest project cost. Poor coating adhesion, inadequate thickness, coating damage, insufficient inspection, or incomplete documentation can lead to repair work, delays, or additional site costs. A practical comparison should include: Pipe specification + coating specification + inspection + documentation + packaging + delivery. At Hunan Great Steel Pipe, coating requirements are reviewed together with pipe specifications, inspection requirements, packaging, and project delivery conditions before production. Our steel pipe products are supplied to customers in more than 80 countries, supporting international pipeline and infrastructure projects.
Practical 3PE Steel Pipe Selection Checklist
Before placing an order, confirm:
-
Application: Where will the pipeline operate?
-
Environment: What external corrosion risks exist?
-
Pipe: What grade, diameter, wall thickness, and length are required?
-
Coating: Which standard and coating requirements apply?
-
Inspection: Which tests and documents are mandatory?
-
Field joint: How will the welded joints be protected?
-
Delivery: How will the coating be protected during transportation and installation?
FAQ
Q1: What should I specify when ordering 3PE steel pipe?
A1: Specify the steel grade, dimensions, manufacturing standard, coating standard, coating requirements, inspection and testing requirements, pipe-end condition, documentation, packaging, and delivery requirements.
Q2: Is 3PE coating suitable for buried pipelines?
A2: 3PE is widely used for external corrosion protection of buried and submerged pipeline systems. Suitability should always be confirmed against the actual service environment and project specification.
Q3: How do I choose the required 3PE coating thickness?
A3: The required thickness should be determined by the applicable coating standard, project specification, pipe dimensions, service conditions, and coating class. It should not be selected only by comparing supplier prices.
Q4: Does factory-applied 3PE coating protect field weld joints?
A4: No. Areas exposed during field welding normally require a separate field joint coating system. ISO 21809-3 addresses field joint coating for buried and submerged pipeline systems.
Q5: What inspection documents should buyers request?
A5: Depending on the project, buyers may request coating thickness records, holiday test results, adhesion or peel test reports, dimensional inspection records, material certificates, repair records, and certificates of conformity.
Q6: How can buyers compare different 3PE suppliers?
A6: Compare the complete supply package rather than coating price alone. Review pipe specifications, coating requirements, quality control, inspection documentation, packaging, delivery capability, and the supplier's experience with similar project requirements.